Schedule Management

Project schedule management consists of first defining the project activities. Once the activities for the project have been identified then the project team and the project manager can put these activities in the correct order which they should happen. The resources needed for the activities will need to estimated; resources are people, but also materials, equipment, tools, supplies, and facilities. The next step is to estimate the activity durations and then develop the project schedule. Finally the project manager must control the project schedule.

This is a big module that covers six different project management processes. One of the most confusing project management activities is covered in this module: how to calculate project float. Don’t spend too much time on learning how to calculate project float; you won’t have hundreds of PMP exam questions on float. Also consider that you’ll likely use a PMIS to help you find, manage, and use project float in your day-to-day work as a project manager.

There are six videos for Module 6 of the PMP Exam Prep:

Defining the Project Activities

Sequencing the Project Activities

Estimating Activity Resources

Estimating Activity Durations

Developing the Project Schedule

Controlling the Project Schedule

Post to Twitter Post to Delicious Post to Facebook Post to StumbleUpon

{ 3 trackbacks }

Manage Activity Relationships
March 31, 2010 at 9:58 am
Tic-Toc: Hurry Up and Wait
April 2, 2010 at 9:33 am
PPM Community - Programme and Project Management Community Blogs
August 2, 2010 at 8:55 am

{ 5 comments… read them below or add one }

Jx April 22, 2010 at 8:36 am

Estimating Activity Resources is being linked to Define Activities presentation.

Joseph Phillips April 25, 2010 at 9:09 am

Thanks for the heads-up! I appreciate the help and the link is fixed. Best to you!

Dilip Sheth November 11, 2010 at 10:33 am

In my 20 +years of working in construction management field, no one has simplified the ES/EF, LS/LF calculations as you have. You are the scheduling GURU. I had just appeared in my PE (Civil) last month, I wish I had reviewed this earlier.
Dilip

Dilip Sheth November 11, 2010 at 10:54 am

In my 20 +years of working in construction management field, no one has simplified the ES/EF, LS/LF calculations as you have. You are the scheduling GURU. I had just appeared in my PE (Civil) last month, I wish I had reviewed this earlier.
Dilip

Joseph Phillips March 2, 2011 at 9:37 pm

Thanks! I’m always thrilled to hear comments like this – so glad I was able to help you out beyond the PMP. Best in all your projects!

Leave a Comment